Filling you in on the hectic events of the past 2 weeks....
10th June – 21st June
Greatest apologies,
Firstly for the lack of frequency of my posts, and secondly,
for the huge delay in updating this particular post- trying to recap the
whirlwind of chaos that was mid-June.
But here it is, back-dated.
Owing to my regretful, unwavering optimism, I have forever
been playing catch-up with myself- with every single activity taking about 3
times longer than initially anticipated. So alas, alack, with my deadline
lingering on the 22nd June, I had very, very little sleep in the
past 60 hours and am not even close to completing my designs thanks to the
complicated nature of the model-box.
Hoping to finish the week with a grand sweep of finalising
my costume designs for the principle characters- whose concepts were already designed
and rock-solid, these plans were soon scuppered when the model-box decided to
take as much time as humanly possible.
I made the decision to focus on finishing the set rather
than furthering the costumes because I thought that I needed to make the most
of my access to the Studio Theatre- which would be unavailable to me during the
summer ‘holidays’ due to my relocation back to Brighton.
So sadly, the costume designs that I was itching to finish
had to take a back-seat to the painstaking precision of positioning the poles
of the mezzanine floor of the set.
To go back further, I will briefly recap some of the
activities that have lead me to this point (my deadline).
Firstly, I completed the uniform designs for Claudio and Benedick:
Firstly, I completed the uniform designs for Claudio and Benedick:
One important day was when myself and a specially assembled
team of logical and clever individuals (to help me with practical issues)
tested out the washing-line idea for the first time in the Studio Theatre.
Forever unsure of whether this idea would ever work with the sight-lines, with
the lights, with EVERYTHING…. I was relieved to see that actually, using a
pulley system already erected on the ceiling, the idea worked perfectly.
The pictures below show our experiments, but it is worth
pointing out that this is not exactly HOW the pulley-system will be set up, in
that the idea is that in reality there will be fishing wire attached to points
on the washing lines and that is the bit that will pass through the pulleys, so
as not to tangle and jam the washing.
I then primarily worked on my set model. I made the tree
from grape stalks and the decking from lolly-sticks. All these sort of
activities I thoroughly enjoyed. It was the precision of the mezzanine that was
really wearing me down. I had such a time trying to get the poles in the right
place, at the right angle. The first attempt, it took me about 3 hours to cut
all the poles to the right length and plastic weld them all together JUST FOR
THE WEST SIDE!! Then I realised that there was some sort of discrepancy along
the way, because woe betide me- the West balcony didn’t even FIT in the model
box…. By about 10cm!!!! So somehow there was a difference between the
measurements in my tutor’s google sketchup model, the measurements of the model
box that I had procured from a 1st year, and my scaling ability….
The only way I could see to rectify this was by going-by
what I considered to be the most reliable source- the sketchUp model. So I had
to print out the birdseye-view of the ground-plan of the sketch-up model-
showing the positions of the poles, rescaling it so that the perimeter matched
that of the model box to the mm, and then take the positions of the poles from
there. It’s just a good job I own a large printer. It was a truly arduous task
that took about a whole day to complete.
Then when I went back to the studio theatre to measure the
stairs etc, it was plainly obvious to me that somehow the model still wasn’t as
precise as it should have been. If I had had ANY more time (and patience) I
would have attempted to rectify this, understanding that accuracy within the
modelbox is of utmost importance, however, as it stood, I was already past the
time that I thought I would have the whole model completed by, and I really
didn’t have time to redo all my hard work. I really did try my absolute hardest
throughout the process to be incredibly accurate, but clearly somewhere along
the line I used incorrect data.
It’s just a little heart-breaking to know how much extra
time it cost me to be extra extra precise yet the model, as a result, is not
even accurate. But oh well… you live and learn.
This being my first major set-back, the rest of the
construction of the box tended to follow suit, meaning that despite many sleep
deprived nights, I only finished it to a satisfactory standard just hours
before my hand-in. It was nothing short of a nightmare.
As a result I was incredibly disappointed with myself for
having failed to complete what I saw as an appropriate amount of costume
designs, especially as I had finalised the concept for nearly all of the
principle chaarcters in my head. Therefore, I spent my final hour trying my
absolute hardest to represent my ideas roughly for each costume. This is
pictured below.
It’s very scrappy and the colours are a bit off, but I am so
glad that I did it.
Coming back to it now, after a long break- I am so glad that
I crystallized these ideas in a semi-realised state so that I could easily
pick-up where I left off.
Now I am back in Brighton and desperately need to start the
ball rolling again in terms of getting the designs back on track.
However, if there is one thing I have learnt from this
project it’s that taking long breaks (even if it is to do 2 beneficial work
placements) can only hinder your progress…. As it takes so much longer to get
back into the swing of the project. The key is to stay focussed- it saves you
time in the long run. This project is becoming a real juggling test for me- but
time will only tell how I balance working at the V&A performance department,
finishing my costume designs, finishing my set model, beginning to source
fabric and props, working as a costume supervisor for 3 shows at the Edinburgh
Festival, learning to drive, and trying to hold-down my summer job at the
theatre in Brighton. Plus it would be nice to fit-in a holiday somewhere down
the line- I have been working so so hard this year and I don’t want to burn-out
just in time for getting the show ready.
But Hey Nonny-nonny. Sigh No more.
No comments:
Post a Comment